End User
National Grid
Client
GE Vernova
Project Title
TP141 Settings Calculations and Verification for Iver 400/275kV SGT6A and 6B (Specialist Support)
Year
2023
Project Scope
The scope covers preparation of TP141 calculations and verifications undertaken by 2 independent authorised TP141 Engineers.
Our Scope
This scope includes:
- Review of suppliers’ design drawings
- Review of supplier Functional design specification
- Preparation of settings reports using standard template for P643
- Preparation of SET, PSL, CH21, MARs sheets
- Setting comparison document against the type-registered SET file
- Upload into NG LiveLink